WASHINGTON - The U.S. Department of Energy issued emergency Order No. 202-26-52 on Nov. 20 directing regional grid operator PJM Interconnection and Constellation Energy to keep Units 3 and 4 of Pennsylvania's Eddystone Generating Station available from Nov. 21 through Feb. 18, 2027.

Order Preserves 760 Megawatts for Winter Peak Demand

Originally slated to retire on May 31, 2025, the two dual-fuel steam units each provide 380 megawatts of capacity, totaling 760 megawatts that can burn natural gas or oil. Under Section 202(c) of the Federal Power Act, PJM must keep the units ready for dispatch while running them economically only during hours needed to prevent mid-Atlantic grid emergencies. "President Trump and the Energy Department are committed to keeping critical generation available when demand is highest, reducing the risk of blackouts and ensuring Americans have affordable, reliable, and secure power," Energy Secretary Chris Wright said in the Nov. 20 announcement.

Repeated Extensions Follow Data Center Load Growth

The roughly 90-day directive extends a series of emergency orders that began on May 30, 2025, immediately after a prior order covering Aug. 23 through Nov. 20, 2026 expired. Federal energy assessments warn that rapid electricity demand from data centers and earlier plant retirements have tightened reserve margins across PJM's mid-Atlantic network.

Environmental Groups Question Ongoing Fossil Extensions

Environmental and consumer advocates, including the Sierra Club and Natural Resources Defense Council, have challenged earlier Eddystone extensions over emissions and compliance costs. The current order expires on Feb. 18, 2027, when federal regulators will review winter grid conditions.