SEOUL - South Korean defense contractor Hanwha Aerospace is constructing a military-only artificial intelligence data center in Changwon. It is a 180-megawatt center. Hanwha Aerospace earmarked 10 trillion won ($7.5 billion) for its first phase. Initial operations are targeted for July 2028.

Facility Capacity Equals 13 Percent of a Nuclear Reactor

The Korea Herald reported. "Hanwha Aerospace said Tuesday it is building a defense AI data center in Changwon, South Gyeongsang Province, with initial operations targeted for July 2028 and an eventual capacity of 180 megawatts,"

It spans roughly 43,000 square meters. It sits next to Hanwha's Changwon plant. High-density GPU servers fill the center. The center anchors a broader 55 trillion won group investment plan announced in July.

Air-Gapped Architecture Supports Manned-Unmanned Teaming

Hanwha told officials on Nov. 24. They were visiting National AI Strategy Committee and Defense Acquisition Program Administration officials. Defense workloads cannot rely on commercial facilities. Military AI requires separated networks, top-tier security, and uninterrupted disaster resilience.

A model is being reviewed. South Korea's military would retain data ownership. Defense contractors operate the site.

Private Build Cuts Four to Five Years Off Timeline

Hanwha estimates the facility will accelerate military AI adoption. The acceleration is four to five years. A Defense Ministry-led build requires six to eight years. Hanwha may bundle data centers into future arms export packages.

Sources

Found a factual error or typo? Tell us